Project #: | 07-29 |
Detailed Status: | Project Closed |
Building Gross Sq. Ft: | 147,607 |
Campus: | ×ÔοÊÓƵ Lubbock |
Location: | 3016 18TH Street |
Budget |
Board Approved Budget: | $7,400,000 |
Adjusted Budget: | $7,647,661 |
Budget Summary: | Additional funding approved for the brick and joint repair. |
Final Cost: | $6,233,542 |
Schedule |
Construction Start Date: | 04.30.2011 |
Project Completion: | 09.15.2013 |
Project Team |
Program Director: | Rick Richeda |
Contractor: | Sandia Construction |
Design Professionals: | Parkhill, Smith & Cooper; EFI |
Artist: | Robert Bruno |
Art Title: | Untitled |
Description |
Installation of a fire suppression and notification system as well as other life safety upgrades to the existing multi-story College of Architecture building. This project will bring the Architecture building into compliance with State Fire Marshal requirements. |