Project Details
Jones AT&T Stadium NEZ Facilities
Project #: | 10-12 |
Detailed Status: | Project Closed |
Building Gross Sq. Ft: | 11,482 |
Campus: | ×ÔοÊÓƵ Lubbock |
Location: | 6 Red Raider Avenue |
Budget | |
Board Approved Budget: | $1,300,000 |
Adjusted Budget: | $1,300,000 |
Final Cost: | $1,109,951 |
Schedule | |
Construction Start Date: | 06.19.2010 |
Project Completion: | 09.17.2010 |
Project Team | |
Program Director: | Ross John Narvaeth |
Contractor: | Lee Lewis Construction |
Design Professionals: | Ross John Narvaeth |
CM Agent: | N/A |
Description | |
Construct 7,000 GSF Build-Out under the seating stands to include Toilets and Concessions. Project provides an additional 24 WCs for women and 21 plumbing fixtures for men; 6 Lavatories for women and 5 for men. Project also includes Concessions infrastructure; build out by Ovations. |