Project Details

Exercise & Sports Sciences

Project #:10-13
Detailed Status:Project Closed
Building Gross Sq. Ft:41,662
Campus:×ÔοÊÓƵ Lubbock
Location:3204 Main Street
Budget
Board Approved Budget: $7,200,000
Adjusted Budget: $7,649,412
Budget Summary:Additional funding approved for the Dance program integration, concrete paving installation, and Phase 3 furniture.
Final Cost: $7,540,645
Schedule
Construction Start Date:02.07.2011
Project Completion:04.11.2012
Project Team
Program Director:Rick Richeda
Contractor:Western Builders of Amarillo
Design Professionals:Condray Design Group; Fanning, Fanning & Associates; EFI Global
CM Agent:N/A
Artist:Nancy Lovendahl
Art Title:Flowmotion
Description
"Exercise & Sports Sciences" This project relocated the ESC department to the former 31,227 gsf Printech facility. The renovated facility supports cardio related labs, intervention labs, motor behavior and biomechanics labs, sport and exercise psychology labs, offices, classrooms and support space.