Project Details
Admin Bldg - 3rd Floor Interior Finish-Out
Project #: | 11-18 |
Detailed Status: | Project Closed |
Building Gross Sq. Ft: | 116,671 |
Campus: | ×ÔοÊÓƵ Lubbock |
Budget | |
Board Approved Budget: | $2,400,000 |
Adjusted Budget: | $2,753,509 |
Final Cost: | $2,745,414 |
Schedule | |
Construction Start Date: | 04.25.2012 |
Project Completion: | 08.24.2012 |
Project Team | |
Contractor: | J.T. Vaughn Construction |
Design Professionals: | SLS Partnership, Inc. |
CM Agent: | N/A |
Description | |
Interior finish-out of approximately 13,040 GSF on the 3rd floor of the Administration Building. Project will include interior partitions, MEP, and finishes for offices, office suites and a conference area. Also includes minor upgrades to the East and West Wings in addition to the 13,040 GSF. |