Project Details
Creative Movement Studio
Project #: | 12-05 |
Detailed Status: | Project Closed |
Building Gross Sq. Ft: | 9,597 |
Campus: | ×ÔοÊÓƵ Lubbock |
Budget | |
Board Approved Budget: | $2,200,000 |
Adjusted Budget: | $2,212,500 |
Final Cost: | $2,164,040 |
Schedule | |
Construction Start Date: | 02.03.2012 |
Project Completion: | 01.30.2013 |
Project Team | |
Program Director: | Rick Richeda |
Contractor: | Western Builders of Amarillo |
Design Professionals: | Condray Design Group; Fanning, Fanning & Associates |
CM Agent: | N/A |
Artist: | Mark Chew |
Art Title: | The Fire Inside |
Description | |
The project will renovate the gymnasium currently associated with the Exercise Sciences Center for the relocation of the dance program. The space will include accommodations for the Texas Tech Cheer and Pom Squads. The scope will include a large (3,500 sf) studio, a small (2,000 sf) studio, a 2,100 sf classroom, men and women locker areas, office suite and associated storage. |