Project Details

Video Scoreboard Package

Project #:12-12
Detailed Status:Project Closed
Building Gross Sq. Ft:3,420
Campus:×ÔοÊÓƵ Lubbock
Budget
Board Approved Budget: $11,000,000
Adjusted Budget: $11,000,000
Schedule
Construction Start Date:12.04.2012
Project Completion:09.06.2013
Project Team
Program Director:Ross John Narvaeth
Contractor:Vaughn Construction
Design Professionals:MWM Architects, Inc.; Rogers Moore Engineer; Anthony James Partners, LLC
CM Agent:N/A
Description
This project constructs a super-structure that spans over the Athletic Ticket Office building at the Jones AT&T Stadium north end zone. The structure supports a state-of-the-art, high-definition video screen and surrounding sponsor screens and graphics. The project also includes video display panels (ribbon boards) and a new sound system that uses the latest digital audio technology.