Project Details

Jones AT&T Stadium North End Zone Colonnade & Infill Seating

Project #:13-02
Detailed Status:Project Closed
Campus:×ÔοÊÓƵ Lubbock
Budget
Board Approved Budget: $5,350,000
Adjusted Budget: $5,401,078
Budget Summary:Additional funding approved to fund the added fence and gate.
Final Cost: $5,395,347
Schedule
Construction Start Date:12.06.2012
Project Completion:11.15.2013
Project Team
Program Director:Ross John Narvaeth
Contractor:Vaughn Construction
Design Professionals:MWM Architects, Inc.
CM Agent:N/A
Artist:United Commercial Cast Stone
Art Title:Untitled (15 medallions)
Description
This project constructs an 800' long, 50' tall colonnade on the north end zone of the Jones AT&T Stadium. Two new infill seating areas with a capacity of approximately 364 new spectator seats plus a party deck complete the northend zone part of the stadium.