Project Details

Jones AT&T Stadium North End Zone Building Renovation

Project #:14-19
Detailed Status:Project Closed
Building Gross Sq. Ft:7,943
Campus:×ÔοÊÓƵ Lubbock
Budget
Board Approved Budget: $4,650,000
Adjusted Budget: $4,650,000
Final Cost: $4,573,429
Schedule
Construction Start Date:12.16.2015
Project Completion:09.03.2016
Project Team
Program Director:Steve Forman
Contractor:Teinert Commercial Building Servcies
Design Professionals:MWM Architects, Inc.
CM Agent:N/A
Artist:Larry Simmons and Tony Greer
Art Title:Illuminated Rider