ASU Hunter Strain Engineering Laboratories Addition

Project #:15-01
Detailed Status:Complete
Building Gross Sq. Ft:9,000
Campus:ASU San Angelo
Location:2225 Vanderventer
Budget
Board Approved Budget: $4,000,000
Adjusted Budget: $4,000,000
Schedule
Construction Start Date:10.02.2015
Project Completion:06.30.2017
Project Team
Program Director:Cody Guins
Contractor:Western Builders
Design Professionals:Kinney Franke Architects, Inc.
CM Agent:N/A
Artist:Doyle Dickerson Terrazzo
Art Title:31.4638°N, 100.4370°W
Description
The project will construct an approximate 11,000 gross square feet addition to the east side of the existing Vincent Building to house four laboratories, one office, restrooms, and support spaces. A new service drive will be accessible to two of the labs on the north side of the facility. Equipment provision and installation is included to support the teaching components of the program. Also, the project includes site work, landscape enhancements, and public art.