Project Details
Music Building
Project #: | 18-08 |
Detailed Status: | Project Closed |
Campus: | ×ÔοÊÓƵ Lubbock |
Budget | |
Board Approved Budget: | $100,000 |
Adjusted Budget: | $10,000 |
Final Cost: | $91,594 |
Project Team | |
Program Director: | Denise Hostick |
Design Professionals: | DLR Group |
CM Agent: | n/a |